Service Requirements - Subdivisions

Developers should note the following requirements when planning for power in subdivisions.

  1. Roads must be cut in.
  2. Survey must be complete and property lines marked with lot numbers.
  3. The staking engineer (Allen Green or Dwayne Douglas) will need a platte to design our lines and maps. The platte must indicate a 20 foot easement behind the survey stakes.
  4. Prior to construction, each lot should be numbered and a $150 fee per lot must be paid.

 